Rio Tinto Fer & Titane — Primary metals
All success stories
Rio Tinto Fer & Titane — logoFER & TITANE

Case study — Primary metals

Rio Tinto Fer & Titane

Maintenance cost reduction through optimization of maintenance strategies.

Mandate duration
12 months
Scope
Material handling equipment and auxiliary services
Pillar engaged
Maintenance strategy optimization

Context

65% reduction in maintenance plan costs

On a continuously operating material handling fleet, the preventive program demanded thousands of hours per year. A large share of those hours went to intrusive, fixed-frequency tasks on components whose failure behaviour no longer justified them.

The problem

What we observed on the floor before the intervention.

  • Oversized preventive program: fixed frequencies inherited from original OEM recommendations.
  • Systematic teardowns introducing infant-mortality failures of their own.
  • No condition data exploited even though the instrumentation already existed.
  • Maintenance plan cost invisible per equipment, therefore never arbitrated.
  • Failure history inconsistently coded in the CMMS.

Our solution

The approach deployed with the crews, from diagnosis to autonomy.

  1. 01Analysis of dominant failure modes from recoded CMMS history and field interviews.
  2. 02Task-by-task review of the preventive plan: tasks without an associated failure mode removed, frequencies adjusted to observed real service life.
  3. 03Systematic teardowns shifted to condition-based inspection: vibration, thermography, oil analysis.
  4. 04Retained job plans standardized and alert thresholds embedded in the CMMS.
  5. 05Gains costed per equipment and presented as a business case validated by operations.

Case study

The return on investment

Results measured and validated with the client at the end of the mandate.

65%

reduction in maintenance plan costs

-40%

of non-value preventive hours

+5 pts

availability on targeted assets

0

major failure introduced by the review

Fewer interventions, better targeted. The equipment runs better now that we open it up less often.
Reliability director, client